Master Plan of Water Supply, Sewage, Storm Water in PMR
The cost of the project is Rs. 23.10 cr. and allotted to M/s. Anvi Construction, Sangali by work order dated 19/09/2019. M /s. Unity I.E. World pvt. ltd. Appointed as Project Management Consultancy (PMC) for this work.
Project consist Intake well 4m dia, WTP 5 MLD, Raising main 350 mm dia OPV pipe 10.84 km length ESR 1 lac & 1.5 lac, pumping machinery 30 BHP, Distribution system 100 mm to 400 mm dia OPV pipe 14.85 km.s
Implementing Partner
At present about 65% Work is completed. At present lowering & laying of raw water raising main pipeline work is in progress. But at some locations local land owners objected to lay the pipelines. Due to which work is hampered. To resolved this issue proposal is submitted to collector office. Notices to concern land owner are issued by Tahsildar.
At present about 65% Work is completed. It is proposed to complete the scheme by March 2023.